Articles by Devlyn Tedesco
FERC May 2024 Open Meeting Preview
It's a busy time for the Federal Energy Regulatory Commission (the "Commission" or "FERC"). In March 2024, FERC issued Order No. 2023-A upholding its major generator interconnection reform order, Order No. 2023. FERC followed that major ruling with two other big actions just six weeks later, issuing two landmark orders—Order No. 1920 (pertaining to long-term transmission planning) and Order No. 1977 (FERC's backstop transmission siting procedures)—on May 13, 2024, at a special open meeting.
FERC May 2024 Open Meeting Preview | JD Supra
It’s a busy time for the Federal Energy Regulatory Commission (the “Commission” or “FERC”). In March 2024, FERC issued Order No. 2023-A upholding its major generator interconnection reform order, Order No. 2023. FERC followed that major ruling with two other big actions just six weeks later, issuing two landmark orders—Order No. 1920 (pertaining to long-term transmission planning) and Order No. 1977 (FERC’s backstop transmission siting procedures)—on May 13, 2024, at a special open meeting.
Order No. 1920: A Guide To FERC's Landmark Transmission Planning Order
At a special Open Meeting held May 13, 2024, the Federal Energy Regulatory Commission ("Commission" or "FERC") issued a long-awaited order on regional transmission planning and cost allocation: Building for the Future Through Electric Regional Transmission Planning and Cost Allocation, Order No. 1920, 187 FERC ¶ 61,068 (2024) ("Order No. 1920" or the "Final Rule"). The Final Rule comes approximately 13 years after Order No. 1000, the Commission's last major transmission reform directive.
Through The RAPID Act, The NYPSC Is Losing Jurisdiction Over Transmission Siting - Or Is It?
The Renewable Action Through Project Interconnection and Deployment ("RAPID") Act, initially introduced in January 2024 through Governor Hochul's 2025 Executive Budget Proposal, was approved as part of the New York budget in April 2024, and the Governor's signature is expected soon.
Through the RAPID Act, the NYPSC is Losing Jurisdiction Over Transmission Siting – Or Is it? | JD Supra
The Renewable Action Through Project Interconnection and Deployment (“RAPID”) Act, initially introduced in January 2024 through Governor Hochul’s 2025 Executive Budget Proposal, was approved as part of the New York budget in April 2024, and the Governor’s signature is expected soon.
FERC April 2024 Open Meeting And May 2024 Open Meeting Preview
* We have updated this alert to correct errors in our original post in its description of the subject matter at issue in Federal Energy Regulatory Commission Docket No. ER24-340.
FERC April 2024 Open Meeting and May 2024 Open Meeting Preview | JD Supra
* We have updated this alert to correct errors in our original post in its description of the subject matter at issue in Federal Energy Regulatory Commission Docket No. ER24-340.
NYISO Pushes Back Anticipated Compliance, Cluster Study Dates After FERC Order No. 2023-A
Interconnection reform is coming to New York State—right on (a slightly revised) schedule. In response to the issuance of a rehearing and clarification order on Federal Energy Regulatory Commission ("FERC") Order No. 2023 ("Order No. 2023") in late March, the New York Independent System Operator, Inc.
NYISO Pushes Back Anticipated Compliance, Cluster Study Dates After FERC Order No. 2023-A | JD Supra
Interconnection reform is coming to New York State—right on (a slightly revised) schedule. In response to the issuance of a rehearing and clarification order on Federal Energy Regulatory Commission (“FERC”) Order No. 2023 (“Order No. 2023”) in late March, the New York Independent System Operator, Inc.
A Complete Guide To Order No. 2023-A, FERC's Interconnection Reform Rehearing Order - Energy Law - United States
On Thursday, March 21, 2024, the Federal Energy Regulatory Commission ("Commission" or "FERC") issued its much-anticipated Order on Rehearing and Clarification on Order No. 2023 ("Order No. 2023-A"). In Order No. 2023-A, FERC acted on 31 rehearing or clarification topics requested by parties interested in the interconnection reforms announced last summer as Order No. 2023.
Additional Delays On Energy Storage Roadmap Inject Additional Uncertainty Into New York's Energy Storage Market - Energy Law - United States
Late last week, the New York State Department of Public Service ("DPS") and the New York State Energy Research and Development Authority ("NYSERDA") issued a long-awaited update ("Update") on the 6 GW Energy Storage Roadmap, which was originally filed on December 28, 2022 ("Roadmap") and identifies "market reforms and cost-effective procurement mechanisms" necessary to help achieve the State's energy and climate goals, including 6 gigawatts of energy storage by 2030.
Energy Storage Sands Continue To Shift At Last NYISO Task Force Meeting Before Order No. 2023 Compliance Filing - Energy Law - United States
On Friday, March 15, 2024, the NYISO hosted what is expected to be the last of its Interconnection Issues Task Force ("IITF") meetings before making its FERC Order No. 2023 compliance filing on April 3, and it was clear that issues remain, in particular, concerning the treatment of energy storage resources.
Additional Delays on Energy Storage Roadmap Inject Additional Uncertainty into New York’s Energy Storage Market | JD Supra
March 22, 2024 To embed, copy and paste the code into your website or blog: Late last week, the New York State Department of Public Service (“DPS”) and the New York State Energy Research and Development Authority (“NYSERDA”) issued a long-awaited update (“Update”) on the 6 GW Energy Storage Roadmap, which was originally filed on December 28, 2022 (“Roadmap”) and identifies “market reforms and cost-effective procurement mechanisms” necessary to help achieve the State’s energy and climate...
FERC March 2024 Open Meeting Preview
The Federal Energy Regulatory Commission ("FERC" or "Commission") will host its March Open Meeting on Thursday, March 21, 2024. The Sunshine Act Meeting Notice, issued March 14, 2024, indicates that FERC intends to take action on several items of note to generation, storage, and transmission developers, some of which we highlight below.
Energy Storage Sands Continue to Shift at Last NYISO Task Force Meeting Before Order No. 2023 Compliance Filing | JD Supra
On Friday, March 15, 2024, the NYISO hosted what is expected to be the last of its Interconnection Issues Task Force (“IITF”) meetings before making its FERC Order No. 2023 compliance filing on April 3, and it was clear that issues remain, in particular, concerning the treatment of energy storage resources.
FERC February 2024 Open Meeting Preview
The Federal Energy Regulatory Commission ("FERC") will host its February Open Meeting on Thursday, February 15, 2024. The Sunshine Act Meeting Notice ("Notice") issued February 8, 2024, indicates that FERC intends to take action on several items of note for developers.
FERC February 2024 Open Meeting Preview | JD Supra
The Federal Energy Regulatory Commission (“FERC”) will host its February Open Meeting on Thursday, February 15, 2024. The Sunshine Act Meeting Notice (“Notice”) issued February 8, 2024, indicates that FERC intends to take action on several items of note for developers.
Overhaul Of Major Electric Transmission Siting Process Proposed In 2025 New York State Executive Budget
In last week's State of the State address, New York Governor Kathy Hochul previewed the Renewable Action Through Project Interconnection and Deployment ("RAPID") Act – a proposal to streamline and expedite the siting and permitting of major electric transmission infrastructure in NY to facilitate the achievement of the State's ambitious energy and climate goals established by the Climate Leadership and Community Protection Act ("CLCPA") in 2019.
Overhaul of Major Electric Transmission Siting Process Proposed in 2025 New York State Executive Bud | JD Supra
In last week’s State of the State address, New York Governor Kathy Hochul previewed the Renewable Action Through Project Interconnection and Deployment (“RAPID”) Act – a proposal to streamline and expedite the siting and permitting of major electric transmission infrastructure in NY to facilitate the achievement of the State’s ambitious energy and climate goals established by the Climate Leadership and Community Protection Act (“CLCPA”) in 2019.
NYISO Begins To Roll-Out Tariff Revisions For Order No. 2023 Compliance
This post is a continuation of our series covering the New York Independent System Operator, Inc.'s ("NYISO") compliance with Federal Energy Regulatory Commission ("FERC") Order No. 2023. Compliance filings are due to FERC by April 3, 2024. The NYISO has spent the last few months developing its compliance plan for Order No. 2023 and now has a fully-formed proposal that will effectuate its new Cluster Study Process.
FERC January 2024 Open Meeting Preview | JD Supra
The Federal Energy Regulatory Commission (“FERC”) will host its January Open Meeting on Thursday, January 18, 2024. The Sunshine Act Meeting Notice (“Notice”) issued January 11, 2024, indicates that FERC intends to take action on several items of note, some of which will be of particular interest for renewable and battery storage developers.
NYISO Begins to Roll-Out Tariff Revisions for Order No. 2023 Compliance | JD Supra
This post is a continuation of our series covering the New York Independent System Operator, Inc.’s (“NYISO”) compliance with Federal Energy Regulatory Commission (“FERC”) Order No. 2023. Compliance filings are due to FERC by April 3, 2024. The NYISO has spent the last few months developing its compliance plan for Order No. 2023 and now has a fully-formed proposal that will effectuate its new Cluster Study Process.
FERC November 2023 Open Meeting Preview
The Federal Energy Regulatory Commission ("FERC") will host its November Open Meeting on Thursday, November 16, 2023. The Sunshine Act Meeting Notice issued November 9, 2023 indicates FERC's intent to act on several noteworthy items, some of which will be of particular interest for renewable and battery storage developers.
Partial Compliance Filing
This post is the second in our ongoing series following the NYISO's compliance with FERC Order No. 2023. In today's post, we cover the NYISO's November 3, 2023 partial compliance filing made with FERC, as well as provide an update on the November 2 Interconnection Issues Task Force ("IITF") Meeting. On November 3, the NYISO made a partial compliance filing with FERC to begin to transition to the new cluster study interconnection process established by Order No. 2023 ("Filing").
FERC December 2023 Open Meeting Preview - Water - United States
The Federal Energy Regulatory Commission ("FERC") will host its December Open Meeting on Tuesday, December 19, 2023 (originally scheduled for Thursday, December 21, 2023). The Sunshine Act Meeting Notice ("Notice") issued December 12, 2023 indicates FERC's intent to act on several noteworthy items, some of which will be of particular interest for renewable and battery storage developers.
FERC December 2023 Open Meeting Preview | JD Supra
The Federal Energy Regulatory Commission (“FERC”) will host its December Open Meeting on Tuesday, December 19, 2023 (originally scheduled for Thursday, December 21, 2023). The Sunshine Act Meeting Notice (“Notice”) issued December 12, 2023 indicates FERC’s intent to act on several noteworthy items, some of which will be of particular interest for renewable and battery storage developers.
FERC November 2023 Open Meeting Preview | JD Supra
The Federal Energy Regulatory Commission (“FERC”) will host its November Open Meeting on Thursday, November 16, 2023. The Sunshine Act Meeting Notice issued November 9, 2023 indicates FERC’s intent to act on several noteworthy items, some of which will be of particular interest for renewable and battery storage developers.
NYISO Order No. 2023 Compliance Update: Summary of November 3 Partial Compliance Filing and Summary of November 2 Interconnection Issues Task Force Meeting | Foley Hoag LLP - Energy & Climate Counsel - JDSupra
This post is the second in our ongoing series following the NYISO’s compliance with FERC Order No. 2023. In today’s post, we cover the NYISO’s November 3, 2023 partial compliance filing made with FERC, as well as provide an update on the November 2 Interconnection Issues Task Force (“IITF”) Meeting.
FERC Extends Order No. 2023 Interconnection Rule Compliance Filing Deadline to Spring 2024 | JD Supra
On October 25, 2023, the Federal Energy Regulatory Commission (FERC) issued an order extending the deadline for Transmission Providers to submit compliance filings to implement the requirements of FERC’s Order No. 2023, which adopted reforms aimed at ensuring that electricity transmission system interconnection customers can interconnect to the transmission system reliably, efficiently, and without undue discrimination.
DOE Releases Roadmap and RFI on Transmission System Interconnection Reform Roadmap | JD Supra
On October 25, the Department of Energy issued a Request for Information (“RFI”) on its draft Transmission System Interconnection Roadmap (“Roadmap”), issued the same day. The draft Roadmap provides a series of recommendations intended to improve the transmission system interconnection process to facilitate the reliable, rapid, and equitable deployment of clean energy resources.
DOE Releases Roadmap and RFI on Transmission System Interconnection Reform Roadmap
On October 25, the Department of Energy issued a Request for Information (“RFI”) on its draft Transmission System Interconnection Roadmap (“Roadmap”), issued the same day. The draft Roadmap provides a series of recommendations intended to improve the transmission system interconnection process to facilitate the reliable, rapid, and equitable deployment of clean energy resources.
FERC Generator Debrief: October Open Meeting Yields Orders Mandating Standards for Inverter-Based Resources and Acceptance of ISO-NE Proposal on Storage-As-Transmission-Only Asset | Foley Hoag LLP - Energy & Climate Counsel - JDSupra
At its October Open Meeting, FERC approved ISO-NE’s proposal to permit energy storage resources to operate as transmission resources, issued a final rule mandating the adoption of reliability standards for Inverter-Based Resources, considered FERC Order No. 881 compliance filings, and took several other actions of note to generation developers and operators. We explore each of these items, below.
FERC Generator Debrief: October Open Meeting Yields Orders Mandating Standards for Inverter-Based Resources and Acceptance of ISO-NE Proposal on Storage-As-Transmission-Only Asset | Energy & Climate Counsel
At its October Open Meeting, FERC approved ISO-NE’s proposal to permit energy storage resources to operate as transmission resources, issued a final rule mandating the adoption of reliability standards for Inverter-Based Resources, considered FERC Order No. 881 compliance filings, and took several other actions of note to generation developers and operators. We explore each of these items, below.
NYISO Previews Order 2023 Compliance Filing at First Meeting of Interconnection Issues Task Force | JD Supra
The NYISO unveiled the framework of its proposed compliance filing for FERC Order No. 2023 (184 FERC ¶ 61,054) to market participants last week at the first meeting of its newly established Interconnection Issues Task Force (“IITF”). This post is the first in a series that will provide updates on the IITF and the NYISO’s Order No. 2023 compliance efforts.
NYISO Previews Order 2023 Compliance Filing at First Meeting of Interconnection Issues Task Force
The NYISO unveiled the framework of its proposed compliance filing for FERC Order No. 2023 (184 FERC ¶ 61,054) to market participants last week at the first meeting of its newly established Interconnection Issues Task Force (“IITF”). This post is the first in a series that will provide updates on the IITF and the NYISO’s Order No. 2023 compliance efforts.
NY Court Upholds NY Public Service Commission's Grant Of Permit To South Fork Wind
Last week, actions by the Second Department of the New York State Supreme Court Appellate Division set the tone for offshore wind development in New York by denying a challenge brought by local opponents to the NY Public Service Commission's ("NYPSC") grant of a Certificate of Environmental Compatibility and Public Need ("CECPN") for the transmission line needed to interconnect New York State's first offshore wind project, South Fork Wind, to the mainland grid.
New York Explores Role of Multiple Technologies in Achieving 100 x 40 | JD Supra
The New York State Public Service Commission (“PSC”) recently kicked off a proceeding to ensure that, by the year 2040, 100 percent of the state’s electricity grid is powered by zero-carbon energy. This proceeding will likely be phased and layered in terms of its topic areas and analyses, but the commencement of this regulatory effort – nearly four years after the requirement was codified in the 2019 Climate Leadership and Community Protection Act (“CLCPA”)– is a major step forward.
New York Explores Role of Multiple Technologies in Achieving 100 x 40
The New York State Public Service Commission (“PSC”) recently kicked off a proceeding to ensure that, by the year 2040, 100 percent of the state’s electricity grid is powered by zero-carbon energy. This proceeding will likely be phased and layered in terms of its topic areas and analyses, but the commencement of this regulatory effort – nearly four years after the requirement was codified in the 2019 Climate Leadership and Community Protection Act (“CLCPA”)– is a major step forward.
NY Court Upholds NY Public Service Commission’s Grant of Permit to South Fork Wind | JD Supra
Last week, actions by the Second Department of the New York State Supreme Court Appellate Division set the tone for offshore wind development in New York by denying a challenge brought by local opponents to the NY Public Service Commission’s (“NYPSC”) grant of a Certificate of Environmental Compatibility and Public Need (“CECPN”) for the transmission line needed to interconnect New York State’s first offshore wind project, South Fork Wind, to the mainland grid.
NY Court Upholds NY Public Service Commission’s Grant of Permit to South Fork Wind
Last week, actions by the Second Department of the New York State Supreme Court Appellate Division set the tone for offshore wind development in New York by denying a challenge brought by local opponents to the NY Public Service Commission’s (“NYPSC”) grant of a Certificate of Environmental Compatibility and Public Need (“CECPN”) for the transmission line needed to interconnect New York State’s first offshore wind project, South Fork Wind, to the mainland grid.
Removing Barriers to Geothermal Heat Pump Deployment in New York | JD Supra
A great deal of progress has been made in decarbonizing the power sector through deployment of clean electricity generation technologies such as wind and solar. But other technologies essential to our efforts to combat climate change, such as geothermal heat pumps, which are critical to decarbonizing buildings (which represented 32 percent of 2019 greenhouse gas emissions in New York State) are only beginning to be deployed at scale.
Removing Barriers to Geothermal Heat Pump Deployment in New York
A great deal of progress has been made in decarbonizing the power sector through deployment of clean electricity generation technologies such as wind and solar. But other technologies essential to our efforts to combat climate change, such as geothermal heat pumps, which are critical to decarbonizing buildings (which represented 32 percent of 2019 greenhouse gas emissions in New York State) are only beginning to be deployed at scale.
Removing Barriers to Geothermal Heat Pump Deployment in New York
A great deal of progress has been made in decarbonizing the power sector through deployment of clean electricity generation technologies such as wind and solar. But other technologies essential to our efforts to combat climate change, such as geothermal heat pumps, which are critical to decarbonizing buildings (which represented 32 percent of 2019 greenhouse gas emissions in New York State) are only beginning to be deployed at scale.
New York’s Energy Storage Roadmap Proposes “Index REC” for Storage | JD Supra
On December 28, 2022, staff of the New York State Department of Public Service (DPS) and the New York State Energy Research and Development Authority (NYSERDA) released the much-awaited New York’s 6 GW Energy Storage Roadmap: Policy Options for Continued Growth in Energy Storage (Roadmap).
New York’s Energy Storage Roadmap Proposes “Index REC” for Storage
On December 28, 2022, staff of the New York State Department of Public Service (DPS) and the New York State Energy Research and Development Authority (NYSERDA) released the much-awaited New York’s 6 GW Energy Storage Roadmap: Policy Options for Continued Growth in Energy Storage (Roadmap).
FERC Grants NYISO Three Year Extension in Implementing Order 2222 | JD Supra
Late last week, the Federal Energy Regulatory Commission granted the NYISO’s mid-November extension request to move the implementation date of certain tariff revisions that will allow distributed energy resources (“DERs”) and DER Aggregations to fully participate in the NYISO’s markets from Q4 2022 to December 31, 2026.
FERC Grants NYISO Three Year Extension in Implementing Order 2222
Late last week, the Federal Energy Regulatory Commission granted the NYISO’s mid-November extension request to move the implementation date of certain tariff revisions that will allow distributed energy resources (“DERs”) and DER Aggregations to fully participate in the NYISO’s markets from Q4 2022 to December 31, 2026.
FERC Grants NYISO Three Year Extension in Implementing Order 2222
Late last week, the Federal Energy Regulatory Commission granted the NYISO's mid-November extension request to move the implementation date of certain tariff revisions that will allow distributed energy resources ("DERs") and DER Aggregations to fully participate in the NYISO's markets from Q4 2022 to December 31, 2026.
FERC Rulemaking State of Play
Federal Energy Regulatory Commission (FERC)-watchers have their eyes squarely on recent reports that Senator Joe Manchin, Chair of the Senate Energy and Natural Resources Committee, won’t schedule a hearing on Chairman Richard Glick’s re-appointment this year, meaning that Glick will leave FERC when his term expires in January 2023. Glick has led FERC in pressing reforms to modernize the country’s transmission system and help bring more renewable and energy storage resources online.
The NYISO Sues the FERC Over Participation of Aggregated Distributed Energy Resources in New York’s Wholesale Markets
The long saga of how small-scale, “distributed” energy resources like energy storage, solar, energy efficiency assets and even electric vehicle charging equipment can participate in the New York State wholesale energy markets, if they “aggregate” their resources and bid together, has now landed in federal court. On October 4, 2022, the New York Independent System Operator, Inc.
Show More
loading
Actions
Is this you?
As a journalist, you can create a free Muck Rack account to customize your profile, list your contact preferences, and upload a portfolio of your best work.Get in touch with Devlyn
Contact Devlyn, search articles and posts on X, monitor coverage, and track replies from one place.
Learn more about Muck Rack