Can a payment claim sent by email be validly served if the respondent never reads it? And if the claimant's follow-up notice of intention to adjudicate is sent before the statutory clock has run, can a good faith attempt by the adjudicator fix the problem? In Rewais v BPB Earthmoving Pty Ltd , the Court of Appeal gave a clear answer to both questions and thereby tightened the screws on compliance. The Rewais family lived on a 103-acre property which they intended to renovate.
Is this you? As a journalist, you can create a free Muck Rack account to customize your profile, list your contact preferences, and upload a portfolio of your best work.
Claim your profile
Articles by Eric Beale
Adjudicator Discretion and Legal Error: Builtcom Constructions v VSD
Whilst not fatal to a determination, it is wrong as a matter of law to strictly apply the Cardno test when determining whether additional material has been duly made. Adjudicators are afforded considerable leeway for mistakes of law in the adjudication process.
Adjudicator Discretion and Legal Error: Builtcom Constructions v VSD
Whilst not fatal to a determination, it is wrong as a matter of law to strictly apply the Cardno test when determining whether additional material has been duly made. Adjudicators are afforded considerable leeway for mistakes of law in the adjudication process. When determining an adjudication application under the (SoP Act), section 22(2)(c) of the SoP Act ostensibly limits the scope of material provided by the claimant which an adjudicator can use to determine the application.
Strictly Served: Unread Emails and Premature Service
Can a payment claim sent by email be validly served if the respondent never reads it? And if the claimant’s follow-up notice of intention to adjudicate is sent before the statutory clock has run, can a good faith attempt by the adjudicator fix the problem? In Rewais v BPB Earthmoving Pty Ltd , the Court of Appeal gave a clear answer to both questions and thereby tightened the screws on compliance. The Rewais family lived on a 103-acre property which they intended to renovate.
A Bad Weekend for Deemed Service: Roberts Co (NSW) Pty Ltd v Sharvain Facades Pty Ltd (Administrators Appointed)
Will a contractual deemed service of email provision ever provide a Respondent more than the statutory maximum 10 Business Days for service of a Payment Schedule? The Court of Appeal's short answer is 'no'. Under section 14(4) of the Security of Payment Act 1999 (NSW) (SoP Act), a respondent must provide to the claimant a payment schedule within the shorter of the time required by the relevant construction contract or 10 business days after the payment claim has been served.
Show More
loading
Actions
Is this you?
As a journalist, you can create a free Muck Rack account to customize your profile, list your contact preferences, and upload a portfolio of your best work.Get in touch with Eric
Contact Eric, search articles and posts on X, monitor coverage, and track replies from one place.
Learn more about Muck Rack