Highlights: * Robex's Kiniero Gold Project, Guinea, remains on track and budget for first gold pour in Q4 CY25. * The Kiniero project remains LTI free (lost time injury) with 4,857,704 hours complete to 30 September 2025. * Mine development activities are tracking according to plan; Mining has commenced on day and night shift with delivery of ore to the Run-of-Mine (ROM) Pad. * Drilling and blasting contractor mobilised to site, with the first blast planned this month.