In an interesting judgment for the construction industry, the TCC in North Midland Building Ltd v Cyden Homes Ltd [2017] considered the enforceability of a bespoke exclusion in respect of concurrent delay and its impact on the `prevention principle'. The judgment confirms that parties can agree at the outset of a contract, who bears the risk of concurrent delay.