Construction has been completed at India’s 5mtpa Mundra LNG terminal in Gujarat but the commissioning process could be postponed because the facility is expected to close over the course of the monsoon season from June to October. The project, led by India’s independent energy infrastructure developer Adani, is also suffering from the lack of a gas pipeline connecting the facility to the target market which will make for reduced operations until late 2019 at the earliest.